The romance of modern engineering, containing interesting descriptions in non-technical language of the Nile dam, the Panama canal, the Tower bridge, the Brooklyn bridge, the Trans-Siberian railway, the Niagara Falls power co., Bermuda floating dock, etc., etc.;
We may conclude the account by a few figures. The bridge is exactly half a mile long, including the approaches, the side spans each occupying 270 feet clear. Its extreme height, measured from the bottom of the foundations to the summit of the main tower ridge-tiles, is 293 feet. The roadway of the side spans is 35 feet wide, flanked on each side by a 121½-foot paved footway. In the central span the widths are reduced by 3 and 4 feet respectively. Its construction, which occupied eight years, consumed 235,000 cubic feet of granite and stone, 20,000 tons of cement, 70,000 cubic yards of concrete, 31 million bricks, and 14,000 tons of iron and steel. The columns on the main piers and abutments required five miles of steel plates.
Romance of Modern Engineering
The total cost was estimated at three-quarters of a million pounds, of which the bridge itself represents rather more than half a million.
Sir J. Wolfe Barry, the engineer responsible for the construction, includes among his other important works the great Barry Dock near Cardiff, and the completion of the Inner Circle Railway between the Mansion House and Aldgate stations.
CHAPTER VI
AMERICAN BRIDGES
The second place among monster bridges is held by the Brooklyn Suspension Bridge, connecting Manhattan Island, on which stands New York Proper, with Long Island. Previously to 1883 New York, with its population of two millions, and Brooklyn, counting a million inhabitants, were kept in communication across a narrow strait, 12 miles long, opening into Long Island Sound, known as the East River, by a number of steam ferries, one of which alone transports 22,000,000 foot passengers and 1,100,000 vehicles annually.
With the growth of population the absence of some permanent connection between the two islands was so severely felt that it was determined to link the two with a bridge of such a height above the water as to offer no obstruction to the shipping passing down the Sound to New York Harbour. The spot selected for the bridge is at the southern end of the East River strait, where it narrows down to a width of rather more than a quarter of a mile.
In deciding on the suspension type, American engineers had two good precedents—the Ohio River and Clifton Suspension at Niagara, which then held
the record in point of span. The Ohio Bridge at Cincinnati had a clear leap of 1000 feet ; while that at Niagara measured 1268 feet between the centres of the towers, standing on either side of the gorge below the Falls. This bridge, opened to traffic in 1869, as a result of but twelve months' work, hung from two cables 1888 feet long, passing over rollers on the summit of the towers, which were built of wood strengthened by massive iron frames. The cables each contained 931 wires, 1-inch diameter, twisted into seven ropes. When loaded with an average amount of traffic the bridge weighed 360 tons. To prevent excessive lateral oscillation strong steel guy ropes were strung from various points on the structure to anchorages on the side of the gorge. After standing and doing useful service for many years, the bridge was destroyed by one of the tremendous hurricanes that periodically sweep down the Niagara gorge as through a funnel.
There remained, however, the Niagara Railway Suspension Bridge, completed in 1855. This has a span of 821 feet, the track passing 245 feet above the river. It should be explained that the lower chord of the bridge is a girder with two floors, the upper of which carries the railroad, while the lower serves for foot and ordinary vehicular traffic. As originally constructed two masonry towers bore the weight of the four cables—each containing 3640 iron wires—that support the girder. After twenty-six years of wear it was discovered that these towers had
American Bridges
been bent inwards to a dangerous extent, owing to the rollers on which the cable saddles work at the tower tops having become clogged with cement. The engineers therefore built iron skeleton towers outside the masonry, and without in any way interrupting the traffic of the bridge, transferred the cables from the stone to the iron supports by means of powerful hydraulic jacks. This is a most interesting feat, and probably unique. When the bridge was in course of construction Robert Stephenson, engaged on the Victoria Tubular Bridge at Montreal, said to the designer of the Niagara Suspension—Mr. John A. Roebling—"If your bridge succeeds, mine is a magnificent blunder." The light American structure did succeed.¹
The Brooklyn Bridge, like that at Niagara, is carried on four main cables. The supports are two huge towers, rising 272 feet above high water. At the river level they measure 140 feet broad by 50 deep, which dimensions decrease to 120×40 feet at the summit.
On the New York side the masonry is carried down to rock 78 feet below water level, giving the tower a total height of 350 feet. The masonry built into the two towers aggregated 85,000 cubic yards. The central span is 1595½ feet. Between the towers and the anchorages are two 930-foot spans ; and beyond these approaches that add 2534 feet to the total length—5989 feet, or about a mile and a furlong.
The most interesting feature of the bridge is the
¹ "The Railways of America," by Thomas M. Cooley.
cable work. Each of the four cables, anchored at either end to massive 23-ton plates, embedded in huge masses of masonry, each representing more than 44,000 tons, contains 5296 galvanised steel wires, which were carried separately from tower to tower, and bound up together in a parallel formation into a cylinder 15 inches in diameter.
The breaking strain of a cable is 12,000 tons. As each strand is 3572 feet long, about 1200 miles of wire were used in the cables.
These support six parallel steel trusses, on which is laid the roadway, 85 feet wide, divided into two carriage-tracks, two tramways, and one footway. The bridge rises towards its centre on a gradient of 3 per cent, the headway increasing from 119 feet at the towers to 135 in mid-channel.
The bridge cost $15,000,000, two-thirds of which was contributed by the Brooklyn municipality, and one-third by that of New York. It was begun in 1870 and opened to the public in 1883. Upwards of a quarter of a million people cross the bridge daily ; but so great is the traffic between Manhattan and Long Island that three more bridges are in course of construction across the East River. These will, when completed, be in the first rank of such structures, and formidable competitors in regard to size with the Brooklyn Bridge.
A traveller in the United States is struck by the versatility of the American bridge-builder, whose genius develops most happily towards the erection
of light, airy viaducts spanning many of the valleys through which the great network of railways run. The States have now nearly 200,000 miles of track laid, and on the average there is one span of metallic bridge for every three miles of railway, giving a total of over 63,000. The increase in weight of locomotives and rolling-stock has led to the renewal of many of these bridges, by the substitution of more substantial work. And the rapid extension of existing systems constantly demands the manufacture of new bridges. Consequently the demand has driven manufacturers to standardise their patterns, and arrive at a distinct understanding with the railway engineers that, except in special cases, where divergence is unavoidable, all bridges ordered shall conform to certain stereotyped designs, which have been decided upon after much experimentation.
The American bridge-building Companies, thanks to this scientific arrangement, and the large number of orders that they are called upon to fill, have advanced the practice of bridge-making to a point that enables them to compete favourably with the manufacturers of other countries. The Yankee railway engineer gives measurements to the bridge Company, which by long practice knows just what is required to meet a particular case, and turns its mechanics, armed with all manner of labour-saving tools, on to cheaply made steel. In a few weeks or months the bridge is ready for delivery, the makers confident that when the pieces are assembled in situ they will come
Romance of Modern Engineering
together "like a clock." Very probably the Company does the erecting as well, so that after the order is given the railway Board's part of the work is confined to handing over a cheque to the proper amount, when the bridge has been passed by their engineers.
On American railroads the trestle bridge is a very common object, often towering to a giddy height, that dwarfs the giant locomotives passing overhead. In 1890 there were in the States 147,187 wooden trestle spans, aggregating 2127 miles of track. These, as liable to insidious decay and danger from fire, are being replaced by steel structures as fast as is possible. A notable instance is the Portage Viaduct on the Erie Railway, New York, crossing a river 234 feet above the bed. The old viaduct contained more than a million and a half feet of timber, arranged in piers formed of three grouped trestles. This was burned in 1875, and in its stead now stands a remarkably slender-looking viaduct of wrought iron, weighing but a small fraction of the wooden structure.
The same railway boasts another remarkable viaduct, the Kinzua, 2400 feet long and 305 feet high. It was built by Messrs. Clarke, Reeves & Co., in the short space of three months, without the use of any staging or ladders. The original spider-like supports have recently been replaced by steel trestles of a more solid nature, better calculated to sustain the great increase of rolling-stock weight.
Outside the country of its birth the American bridge is making headway. In recent years British
American Bridges
builders have several times felt their inability to compete with their transatlantic cousins, when creation and erection has to be hurried through. To take three notable examples. The Atbara Bridge, seven spans of 147 feet, was tendered for by American makers at £10, 13s. 6d. per ton; construction to take six weeks and erection eight weeks. The nearest English tender showed £15, 15s. per ton, and twenty-six weeks. The Uganda viaducts, East Africa, also fell to American makers, since their price was but three-fifths of the English figures. And in the third instance, that of the Gokteik Viaduct, Burma, their price was little more than a half that of British makers, and the contract time one year as against three years. These examples show how unequal is the competition, owing largely to the conservatism of English methods, and the imbecilities of trades-unionism in the British Isles. To "keep his end up" the British manufacturer will need to consign much of his machinery to the scrap heap, adopt standard designs, and instil a spirit of greater enterprise into his employés.
The Gokteik Viaduct, as the loftiest trestle erection in the world, and among the latest born, deserves special notice. It affords a typical illustration of American methods.
The Burma railway, running from Rangoon to Mandalay, a distance of about 400 miles, has lately been extended in an easterly direction through the Shan States to Lashio, en route to the Kunlon Ferry on the Salween River, following the track over which in