The Simplon tunnel will have an ultimate length of 12½ miles, of which 12 are on the straight, the line curving away at the ends to join the open tracks. At the centre there will be a level stretch of about 750 yards. From this the line falls gently on a gradient of 1 in 500 to Baffi, at the Swiss end ; and by a more sudden descent of 1 in 143 to Iselle in Italy. The highest point being but 2314 feet above

sea level, or 1474 feet less than in the case of the St. Gothard, the cost and difficulty of haulage will not be nearly as great as that of the more easterly route, and only one helical tunnel—on the Italian side—is necessary for the approaches.

The Simplon differs from the Mont Cenis and St. Gothard undertakings in that the tracks will run in separate parallel tunnels, the axes of which are 56 feet apart. At present only one of these is being completed to full section (19 feet 6 inches by 19 feet 6 inches). The other will be enlarged from its temporary dimensions (10 feet by 8 feet) as soon as the need arises, at a much smaller cost than the first. Every 220 yards cross-passages are cut between the two tunnels, the most recent only remaining open to promote the proper ventilation of the workings. This subsidiary work, which for distinction’s sake may be styled tunnel No. 2, has also proved most useful for drainage, the storage of material, and as a conduit for the compressed air and water pipes.

The determination of the centre line of so long a tunnel running under a series of lofty peaks is no easy matter. It being impossible to pick out a straight line immediately over the proposed path of the tunnel, mark it, and guide the operations by observations of these marks from time to time, the surveyors, after setting two fixed points, one at each end of tunnel No. 1, had to calculate the path of the excavations by means of triangulations struck from eleven peaks, of which Monte Leone holds the central position.

"The Simplon Tunnel

"On the top of each summit is placed a signal, consisting of a small pillar of masonry founded on rock, and capped with a sharp pointed cone of zinc, 1 foot 6 inches high. An observatory was built at each end of the tunnel in such a position that three of the summits could be seen, a condition very difficult to fulfil on the south side owing to the depth of the gorge, the mountains on either side being over 7000 feet high. Having taken the angles to and from each visible signal, and therefrom having calculated the direction of the tunnel, it was necessary to fix, with extreme accuracy, sighting points on the axis of the tunnel, in order to avoid sighting on to the surrounding peaks for each subsequent correction of the alignment of the galleries. To do this, a theodolite 24 inches long and 2\frac{3}{8} inches in diameter, with a magnifying power of forty times, was set up in the observatory, and about 100 readings were taken of the angles between the surrounding signals and the required sighting points. Thus, at the north end two points were found about 550 yards before and behind the observatory, while on the south side, owing to the narrowness of the gorge, the points could only be placed 82 yards and 176 yards in front. One of these sighting points consists of a fine scratch ruled on a glass in an iron frame, behind which is placed an acetylene lamp—corrections of alignment are always done by night—the whole being rigidly fixed into a niche cut in the rock, and protected from climatic and other disturbing agencies by an iron plate."

231

"The direction of heading No. 1 is checked by experts from the Government Survey Department at Lausanne about three times a year, and for this purpose a transit instrument is set up in the observatory. A number of three-legged iron tables are placed at intervals of 1 mile or 2 miles along the axis of tunnel No. 1, and upon each of these is placed a horizontal plane, movable by means of an adjusting screw, in a direction at right angles to the axis along a graduated scale. On this plane are small sockets, into which the legs of an acetylene lamp and screen, or of the transit instrument, can be quickly and accurately placed. The screen has a vertical slit, 3 inches in height, and variable between 1316\frac{13}{16} inches and 316\frac{3}{16} inches in breadth, according to the state of the atmosphere, and at a distance shows a fine thread of light. The instrument, having first been sighted on to the illuminated scratch of the sighting point, is directed up the tunnel, where a thread of light is shown from the first table. With the aid of a telephone, this light is adjusted so that its image is exactly coincident with the cross hairs, and the reading on the graduated scale is noted. This is done four or five times, the average of these readings being taken as correct, and the plane is clamped to that average. The instrument is then taken to the first table, and is placed quickly and accurately over the point just found (by means of the sockets), and the lamp is carried to the observatory. After first sighting back, a second point is given on the second table, and so on."

The Simplon Tunnel

These points are marked either temporarily in the roof of the heading by a short piece of cord hanging down, or permanently by a brass point held by a small steel cylinder, 8 inches long and 3 inches in diameter, embedded in concrete in the rock floor, and protected by a circular casting, also sunk in cement concrete, holding an iron cover resembling that of a small manhole. From time to time the alignment is checked from these points by the engineers, and after each blast the general direction is given by the hand from the temporary points."1

The accuracy of the surveyor's calculations is one of the greatest marvels of modern engineering. In the Mont Cenis tunnel the error was but a matter of 1 inch in 8 miles ; in the St. Gothard about a foot in 9 miles, quite negligible quantities.

The contractors, Messrs. Brandt, Brandau & Co., of Hamburg, signed in May 1898 the contract for the entire completion of the work by May 13, 1904, or within five and a half years of the commencement on November 21, 1898. For every day in excess of that period a fine of 5000 francs (£200£200) will be imposed, and for every day less the contractors earn a premium of equal amount. Epidemic, war, or mutual lassitude of Italy and Switzerland, are fixed as the only causes for the cessation of work. Should the operations continue for more than a year beyond the stipulated time, the contractors will hand over the execution to the Jura-Simplon Company.

1 From "Tunnelling," by Charles Prelini and Charles S. Hill.

Romance of Modern Engineering

The contract price is 69,500,000 francs, or about £2,780,000.

The progress of the tunnel is shown in the following figures. In 1898, out of a total of 21,564 yards, 447 were completed :—

By the end of 1899.4,227 yards
„19007,947 „
By August 1901.10,790 „
By June 1902.13,345 „

Since then the rate of advance has been steady, and we may expect that, unless some unforeseen obstacle of unusual proportions presents itself, the work will be successfully concluded in contract time.

A simple calculation shows that the average advance from November 1898 to June 1902 was 31 feet a day. During part of this period Sunday was considered a dies non by the workmen ; and the yearly holidays being also subtracted the average then rose to 33 or 34 feet per diem. Compare this with the average 734\frac{3}{4} feet of the Mont Cenis, and the daily 13112\frac{1}{2} feet of the Mount St. Gothard, and the rapid development of the art of tunnelling is evident. In justice to M. Favre we must, however, admit that the total section of the two Simplon tunnels is not equal to that of the single St. Gothard ; but even when due allowance has been made on this head, the contrast in speed is marked.

One of the greatest difficulties in tunnel-driving through mountains arises from the need of proper

ventilation at the working-face. The heat of a tunnel increases with the altitude of the superincumbent mass. At the centre of the Simplon, where 6000 feet of rock cover the workings, the heat would be unendurable but for artificial means of cooling, while the fumes from the explosives would render the air unfit for respiration, were it not constantly replaced by fresh supplies from outside the tunnel.

The plant for ventilation and transmission of power, shops, hospitals, laundries, and other establishments for the convenience of employés, are practically the same at Baffi and Iselle. It will therefore suffice to describe what is seen at the Italian end.

The first thing that attracts our attention is the power-house, containing three Escher-Wyss turbines, two of 250 horse-power, and one of 600 horse-power, running at 170 revolutions per minute. To these are attached ten pumps for supplying water to hydraulic accumulators at a pressure of 1764 lbs. to the square inch. From the accumulators the water passes through 4-inch pipes up the tunnel to the working-face, where it actuates six rock drills, to be described presently.

It is fortunate for the contractor that he can at a comparatively small cost harness the force of the Diveria to his drills. The river has been dammed about 2½ miles above the power-house, and turned into two reservoirs connected with the turbines by large pipes, cast-iron for the first 1440 yards, and then built up of steel plates ¼-inch thick. At the power-

house the pressure of the water is about 250 lbs. to the square inch.

A special pair of 200 horse-power turbines does all the ventilating of the Italian excavations. Each drives a fan 12¼ feet in diameter and 3 tons in weight, which forces air through a 14-inch pipe to the working-face. The pipe is carried along close to the roof of the tunnel, and is added to as the excavation proceeds.

We notice the two electric-light stations each supplying current for 32 arc lamps of 500 candle-power, and 100 16-candle-power bulbs. Passing the machine-tool shop, where are installed lathes, planing machines, saws, &c.—all worked by turbines—we come to the smithy and foundry, a most important part of the workshop. Their principal function is to make and repair cutters for the Brandt borer, invented by and named after the contractor.1

The welfare of the employés has been provided for in the bath-houses, where every miner can have a bath or douche when he leaves the tunnel at the end of his shift ; and in the laundries and drying-rooms, where the dirt and moisture is removed from his clothes. Instead of a locker each man has a numbered cord supporting three hooks, and a soap dish, which, when loaded with their owner’s belongings, are hauled up to the ceiling out of the way, and into the warm upper stratum of air. At the restaurants excellent food is provided for the very moderate sum of


1 Sad to relate, the same fate overtook MM. Favre and Brandt—death from apoplexy before the completion of their great works.

The Simplon Tunnel

11d. a day ; 2d. more ensures the miner a comfortable bed in rooms lit by electric light. So that his bodily needs are well cared for.