Romance of Modern Engineering

naming the construction of a jetty 50 feet wide and 2100 feet long, extending from the South Queensferry shore to the piers of the Queensferry tower. This jetty was a considerable piece of engineering in itself. It carried lines of rails for conveying stores and steelwork to the Queensferry piers, or to barges plying between it and Inchgarvie and Fife.

Ten out of the twelve circular piers, carrying the three towers, were constructed by means of caissons or coffer-dams. These may be described as contrivances for laying dry a space below water-level, or preventing a free flow of water over it. In soft ground a coffer-dam is formed by driving down two circles of long contiguous piles, leaving between the circles a space of a few feet, which is filled in with water-tight clay-puddle. The dam thus formed is provided with sluice gates to let in the water when required. In some cases the water is excluded until half-tide, when the rising pressure may make it expedient to admit water, so as to equalise the pressure on both sides of the dam. When the dam is strong enough to resist high-water pressure, it is called a whole-tide dam, and the space inside can be worked upon continuously.

On rock, recourse is had to steel-sided caissons, the sides being cut to fit the contour of the rock on which they rest, and their bottom edges made water-tight by means to be presently described.

In deep water, where outside pressure becomes very severe, an ingenious structure called a pneumatic

The Forth Bridge

caisson is used. This consists of an upright circular iron cylinder, resembling a gasometer in outline, built of stout plates closely riveted together. Six or seven feet from the bottom a watertight metal diaphragm, or floor, shuts out the lower part of the caisson from the upper air, and so gives it, when the whole is sunk, the properties of an ordinary diving-bell.

Leaving for a moment a further description of the caissons, let us turn our attention to the following table, showing the depth of the deepest points of the twelve piers of the Forth Bridge towers below high water :—

FifeN.W., 7 ft. below high water.
N.E., 7
S.W., 25
S.E., 37
InchgarvieN.W., 23
N.E., 26
S.W., 72 ft. 1 in. below high water.
S.E., 63, 9
QueensferryN.W., 85, below high water
N.E., 89
S.W., 71
S.E., 73

As each of the piers rises 18 feet above high water, the total height of the structure at the north-east of Queensferry tower is 330+89+18=437330 + 89 + 18 = 437 feet !

No dams were required for the Fife north piers. The Fife south piers were built inside steel and wooden pile coffer-dams. In the case of the Inchgarvie north piers, stagings were erected over the

sites of the piers and soundings taken at intervals of 6 inches round the circumference of a 60-foot circle. An iron belt 3 feet deep and 60 feet in diameter was then constructed, and to this were attached vertical steel plates of a length corresponding with the depth of water immediately beneath. As soon as the whole had been completed, the shell was lowered into place, the uppermost part resting in a groove cut in the higher levels of the rock. Rows of concrete bags were then placed outside, and clay rammed between them and the plates until tight joints permitted the pumping out of water at half tide, an operation entailing the removal of 590,000 gallons in less than an hour’s time.

From a reader’s point of view the remaining six caissons—the southern Inchgarvie and all four Queensferry—working on the pneumatic principle, will be of especial interest, and as such merit a more detailed description.

The pneumatic caissons, 70 feet in diameter at the bottom, and of different heights, were erected on the South Queensferry shore; and when complete were loaded with concrete and tools, and launched, to be towed to their final resting-places. These last had already been carefully surveyed by means of a circular raft of planking and timber balks, 70 feet across, having a central upright staff, and a carriage running on a circular rail laid a foot from the outer edge. Attached to the carriage was a drum of steel wire, raising and lowering a 60 lb. weight for taking

soundings. The raft was moored in such a position that its central staff occupied a certain point, determined by instruments, and soundings were made. At South Inchgarvie, where the foundation is sloping rock, piles of sandbags were arranged at the points of greatest depth, so that the caissons should settle on an even keel. These caissons, after being towed into position, were gradually loaded with deposits of concrete until they began to touch ground at low water. Additional piles of sandbags were then placed below in the air-chamber, and the rock was gradually cut away on the high side to make a chase for the caisson to rest upon when loaded sufficiently to lose all its buoyancy at high water. The circular area of bed-rock and the supports were then removed by degrees.

Let us imagine ourselves furnished with the engineers’ permission to visit the “working face” below a caisson. On reaching the deck of the caisson we see a powerful steam crane raising loads of débris out of an air-lock, at the upper end of a tube communicating with the air-chamber 60 feet below. We are ushered into the workmen’s air-lock, a circular chamber with another circular chamber 3 feet 6 inches diameter in its centre. The doors through which we entered are then closed tight, and a tap communicating with the air-chamber opened until the pressure has gradually risen sufficiently to allow the opening of doors in the central tube. We descend ladders, experiencing a sensation

of great oppression on the ears and eyes, and presently find ourselves among the workmen—mostly North Italians, with a sprinkling of Germans, Belgians, French, and Austrians, who have been brought over by M. Coiseau, the contractor, for this part of the work, not as being better physically able to work under such circumstances than Britons, but as more experienced. Powerful electric lights of 200 candle-power illumine the chamber, the sides of which slope outwards towards the bottom, ending in a stout steel cutting-edge. Two men, armed with heavy sledge-hammers, are beating on the top of a crowbar held by a third ; they are drilling or “jumping” holes for blasting charges. As soon as enough are made the charges will be inserted and, when every one has withdrawn, after carefully shielding the lamps, be fired from above by electricity. Then the men will descend again and remove the débris by means of the skips that pass up and down their own air-lock and well. Under one side of the caisson, where piers of concrete bags support the edge, men are thrusting out sandbags that have served their purpose ; and in the gaps we may perhaps see the startled visages of salmon, dogfish, and other denizens of the deep that from time to time are attracted to the glare of the lights within.

In the Queensferry caissons a somewhat different spectacle would present itself. The drills and cement piers are absent ; there is no preparation for blasting, for we stand now on more or less stubborn clay.

the sinking of the caisson is still in its earlier stages, we make the acquaintance of the air-ejector for discharging the silt that mixes readily with water. A man standing in the muddy mixture lowers to its surface the nozzle of a hose, and another man turns on a large tap that controls the passage of the compressed air of the chamber to the outer atmosphere. As soon as the tap is opened a rush of air takes place, and the nozzle being dipped into the liquid some of the latter is carried up the hose by the momentum of the air and shot out at the farther end of the piping in intermittent spurts. The rate of ejection depends largely on the skill of the operator.

On reaching the hard and stubborn clay below the silt, the workmen’s energies become unequal to the task of removing the “spoil” by mere muscular effort. The forces of nature are now called in. An hydraulic spade, the invention of Mr. Arrol, is set up. A word about this spade. It is, described briefly, an hydraulic ram working at a pressure of 1000 lbs. per square inch. To its lower end is attached a large spade, and to its top a headpiece. Two men fix it vertically, with its head against the roof of the chamber, and another turns on the water, which with giant strength forces the spade into the boulder clay, detaching a slice 16 to 18 inches deep and 4 inches thick. The spade is then moved on a little, and the operation repeated until trenches have been cut all over the bottom.

The air-pressure under which the excavators had

to work rose on occasions as high as 40 lbs. to the square inch, yet not a single death can be directly attributed to these abnormal conditions. "The principal bad effect produced by the air-pressure," says Mr. Westhofen, "appears to be that of severe pains in the joints and muscles of the arms and legs. As these have been in most cases traced to hard work and copious perspiration, and also to too long a stay under pressure, it has been suggested as a probable cause that small globules of air make their way through the skin, or between the skins, where they remain and, on the workmen returning to ordinary atmospheric pressure, expand, and thereby cause the most agonising pains in the joints, the elbows, shoulders, knee-caps, and other places. In seeming confirmation of this the sufferers got instant relief on returning to high pressure. Thus it happened that many of those afflicted with this disorder spent the greater part of Saturday afternoon and Sunday under air-pressure, and only came out when absolutely obliged to do so. Various researches were made by members of the medical staff in the endeavour to give relief or obtain a cure, but, so far, not with any degree of success."

Owing to the nature of the river bottom the sinking of the Queensferry caissons was a matter of much anxiety to the engineers. At low water especially, when the cutting-edge bore down with greatest force, a sudden settlement was to be feared, and therefore the men were then generally withdrawn ; a precau-

Photograph of the Fife cantilever at the Forth Bridge, with a large steel structure extending from a pier, a crane, and workers on a platform.
From a photo lent by [Sir Benjamin Baker] THE FIFE CANTILEVER, FORTH BRIDGE This illustration gives a good idea of the complex steelwork at the meeting-places of the chief members of this bridge. The horizontal tube over the pier, to which the tower column and diagonal support, besides the strut and bottom member of the cantilever, are fastened, is called a “skewback.” To the extreme right are seen a riveting cage and a crane, which move forward with the extension of the cantilever

tion that on one occasion at least was amply justified, for the caisson without warning sank 7 feet, filling not only the air-chamber but also part of the air-lock shaft with mud and silt.

The most serious accident that took place during the building of the bridge happened to the north-west caisson of Queensferry. It had been towed into position during high tide, and at the ebb took the ground so firmly that, an unusually high tide occurring soon afterwards, it filled and canted over. The consequent pumping operations were conducted too fast, and before the caisson could be sufficiently strengthened on the inside the water outside burst in the plates, making a rent about 30 feet long on the lower side. This unfortunate occurrence necessitated the construction of a heavy timber frame round the caisson, and nearly ten months passed before it was afloat again.