This South American line is not an ordinary mountain railway: it is an audacious marvel of engineering science. Nor does it merely offer facilities for sight-seeing among the impressive Cordilleras, but acts as a traffic highway between the coast and the mines on the high inland plateau.

As might be supposed, the difficulties which the engineers had to break down were numerous and stupendous. Moreover, the work was extremely costly. In the case of the Oroya road it averaged about £60,000, or $300,000, per mile, and altogether £8,500,000 ($42,500,000) were sunk in the enterprise—more than the total cost of the St. Gotthard railway, with its famous tunnel and 172 miles of track.

The first attempt to subjugate this range by the iron road was made in the ’sixties by a daring Philadelphia engineer, Henry Meiggs. His idea was ambitious in the extreme. He proposed to start from Callao, lift the metals over the crests of the mountains, drop down the other side on to the highlands, and to push across the plateau until he gained a point on the mighty Amazon which could be reached by steamer from the Atlantic. By this means the Pacific seaports of South America would be brought into closer touch with the markets of the Old World, avoiding the protracted and hazardous journey round Cape Horn. That the idea was never carried to success was one of the sorry tricks of Fate. Internecine strife and wars with neighbouring states sapped the financial strength of Peru to such an extent that there was not enough money to complete this grand scheme. Possibly some day the steel thread will be picked up again at Oroya and forced to its original objective.

For the first 107 miles this railway makes a continual ascent; there is not a single foot of downhill in the whole distance. Work was commenced in 1870, and was pushed forward so energetically that in the course of twelve months Meiggs had completed 20 miles of the line, and had the earthworks well advanced as far as Chosica, some 33 miles out of Callao. In order to ease his task as much as possible, the engineer decided to follow the Rimac River into the mountains. But as the innermost recesses of the Cordilleras are gained, the river narrows considerably, until it plunges merely through a slender defile, the walls of the peaks dropping down precipitously into the water. The result was that the engineer found it very difficult to find a natural lane for his metals, so he had to hew and blast galleries, to swing first from one bank to the other, in order to seize the slightest foothold.

He had plunged 47 miles into the mountains and had gained an altitude of about one mile, when he was brought to a dead stop. The mountain along which he had crawled laboriously broke off abruptly. Further advance was impossible. To have cut a tunnel would have been a herculean task, and as the mountain wall dropped straight down below, and towered to a dizzy height above him, he found himself in a quandary. A few feet immediately above him, however, he espied a ledge running parallel with that on which he had laid his track. He resolved to gain that upper gallery, but the crucial question was, How?

Then he hit upon a brilliant idea. It was something new and untried in railway engineering, but as he had already tested all existing methods to gain the point at which he now stood, there was no alternative but to devise new ways and means of overcoming perplexing situations as they arose, despite the apparent novelty of the solutions. He resolved to lift the track from the lower to the upper ledge by a “V-switch.”

MEIGGS’ MASTERPIECE—THE V-SWITCH, BY MEANS OF WHICH THE RAILWAY IS LIFTED FROM ONE LEVEL TO ANOTHER, SHOWING TURNTABLE AND METHOD OF OPERATION

THE INFIERNILLO BRIDGE

It is approached at either end through a tunnel, and owing to the precipitous cliffs the men had to be slung out from the sides in rope loops and cradles to set the steel.

A HORSESHOE CURVE IN A TUNNEL

The train enters the lower mouth, describes a semicircular turn in the heart of the mountain, and emerges from the upper portal.

The embankment on the outside of the track at the point he had gained was levelled off, and a small turntable was erected. From the latter two short lines were laid down at an angle to the track in the form of a widely opened “V,” with the turntable at the apex. The main line cuts across the top of the “V,” forming a triangle, and continues a short distance beyond. The manner in which the train is lifted from the one level to the other is as follows. The engine pulls it up the lower line on to the section crossing the top of the V, and in such a way as to be between its two angular limbs. The engine is uncoupled, and runs down one leg of the V on to the turntable, which is then swung round until the engine faces the other arm of the V, up which it passes until it gains the main line. It is now at the rear of the train which it was pulling a few minutes before. The engine is coupled up, and the train is pushed backwards until it is over the switch connecting with the upper level. It then proceeds forward in the usual manner. In reality it makes a zigzag course up the mountain-side.

This ingenious means of overcoming such a difficulty was tried first at San Bartholomé, and proved so very economical and simple a solution of a grave difficulty that it was freely introduced by the inventor whenever similar conditions were encountered. True, the process of uncoupling and recoupling the engine occasions a little delay, but the switch was cheaper and quite as effective as a loop, even if the latter could have been built, for it was found possible to lay the turntable between two tiers of metals on a gradient not exceeding 1 in 25. Altogether there are 22 of these switches on the system. The majority of them are of the simple type as we have described above, but in some cases there is a double zigzag when the difference in level was extreme, and did not permit of the connecting bank line being raised at an easy grade. The adoption of the “Meiggs V-switch,” as it is popularly called, saved the engineer thousands of pounds.

In one case the switch is set in a very precarious situation, for the climbing line winds along a perilous ledge blasted out of the solid flank of the peak, and the traveller’s heart thumps every time the train lurches as he looks down upon the curling river far, far below on the one, and the mountain wall combing some 2000 feet above him on the other, hand. The Oroya line has been described as a railway of sensations, and it is an apt description. During the process of “V-ing” a train the voyager has ample opportunity to contemplate his peculiar situation at leisure.

“Highly ingenious and simple,” was the verdict of the railway world when they realised Meiggs’ handiwork. “But what is going to happen if a descending train runs away at one of these switches? Will it make a bee-line for the bottom of the canyon through the air, or pile up against the dead-stop?”

Meiggs, however, did not anticipate trains running amok in this manner, but he guarded against any such contingency, because brakes sometimes will fail to act on a descending grade. Consequently, at the end of each line in a V-switch he provided a substantial bank of earth. This was a fortunate precaution. Some years ago a train, in proceeding from the upper to the lower level, did run away on the falling bank. It crashed into the solid embankment at the dead-end, and came to a stop in an ungainly, heterogeneous mass of twisted ironwork and splintered wood. Nobody was hurt, the debris was removed, and the runaway engine was recovered, overhauled, replaced in service, and is running to-day, little the worse for its misadventure.

Owing to the peaks of the Cordilleras being separated from one another by yawning ravines, extensive bridging became imperative. Some are short, insignificant spans; others are lofty, spidery structures, which were completed at the expenditure of many human lives from disease and accident. As a matter of fact, the railway earned an unsavoury reputation owing to the high mortality that attended its realisation.

The Verrugas bridge was the greatest offender in this respect. It was the greatest undertaking of its type on the line. It is 575 feet in length, and cleaves the air 225 feet above the bed of the ravine. There are bigger and loftier bridges in other parts of the world, but few have been so troublesome to erect. At the time it was undertaken it was the most remarkable structure of its kind, and by the time it was completed £12,600, or $63,000, had been expended. It lies at an altitude of 5,839 feet, and was carried on three masonry piers, the centre and main support being built up from the bed of the gorge. This pier measured 50 feet square at the base, and was of solid masonry, thus forming a substantial plinth for the slender iron superstructure.

All the component parts of this bridge had to be kept within certain limits of dimension and weight, to enable them to be hauled up from the coast and set in position on the site. Large gangs of workmen were crowded upon the work, because, until this bridge was set in position, material could not be transported to the other side of the gorge for the continuation of the grade.

But the task was dogged by ill-luck. Work was in full swing, when a mysterious and malignant disease broke out. So furiously did it rage that the men were swept off like flies. There was no means of checking its ravages. It became known far and wide as the “Verrugas fever.” It resisted diagnosis and treatment, but there was no denying its deadliness. As a result labour gave the district a wide berth. It struck down natives and white men indiscriminately. Just how many men succumbed to the attacks of this epidemic probably never will be known. Men contracted the malady, died, and were buried all within the space of a few hours after reaching the site; indeed, it is chronicled that one man fell a victim after crossing the bridge only once.

This mysterious and terrible scourge threatened to stop the whole enterprise, though Meiggs spared no effort and money to bring about its completion. The most attractive inducements were held out to workmen to come up and risk their lives, but only the more adventurous, fascinated by the high wages, dared to face death in an uncanny form. It was mainly through the efforts of such happy-go-lucky spirits that the gorge was spanned ultimately. Meiggs himself appeared to bear a charmed life, for he haunted the fated gorge day and night. But the awful experience seriously undermined his health, his constitution was wrecked, and he was changed into an old man.

Still he clung tenaciously to his enterprise. The gorge crossed, he found himself among the wildest fastnesses of the Andes. The mountains became steeper, the intervening gulches deeper and more difficult to cross. Landslides were of such frequent occurrence that they might well have struck terror into his heart. Yet he fought his way forward. Blasting became heavier and heavier, wide sweeping curves more frequent, the ascent steeper and steeper, and tunnelling through projecting spurs more frequent.