The Railway Conquest of the World
The location of the railway across this gorge was beset with peculiar difficulties. The question of the approach was trying to decide to the best advantage, and in fact so many surveys were made that one of the American engineers remarked “that he could not see the side of the cliff for survey pegs.”
THE TRAINING-BUND UNDER CONSTRUCTION BY NATIVE LABOUR. AT THE EXTREME RIGHT A PIER IS BEING BUILT FOR THE BRIDGE
GENERAL VIEW OF THE PIER-BUILDING OPERATIONS FOR THE CURZON BRIDGE ACROSS THE GANGES AT ALLAHABAD
The bridge is 3000 feet long. Temporary line at right.
The gorge itself is also somewhat strange; in fact, it is a curious wonder of Nature. The Chungzoune River flows through the rift, but out of sight, its course being through a natural tunnel, into which it disappears suddenly at a depth of 500 feet. When the line was first surveyed it was in accordance with a low viaduct, the approach thereto being over a suggested section of rack railway working on the Abt system, with grades of 1 in 12½. This was subsequently abandoned, and the surveyor was called upon to find a fresh location so as to eliminate the rack railway, and to give grades not exceeding 1 in 25, so as to permit the line to be worked by adhesion. This decision raised the height of the towers by 70 feet and increased its length to 1,350 feet. Even this did not meet with approval, for after prolonged deliberation a third location was demanded, to give an easier line yet. In this last survey the gradients were flattened to 1 in 40, with an attendant increase in the height of the structure as well as of its length. It was found impossible to improve upon the viaduct itself, so further surveys were carried out to improve the approaches, reducing their length and introducing curves at either end of the viaduct.
At last finality was reached, and the contract was secured by the American bridge-builders on April 28, 1899. They lost no time in hurrying forward the preparation of the steel. Three months later a special train of 45 cars, laden with 977 tons, left Steelton on the 201-miles run to New York, where a specially chartered steamer was in waiting to receive this steel cargo. The vessel left the American port on a journey of over 10,000 miles to Rangoon, where the freight was transferred to the small trucks of the railway and sent on the up-country journey of 460 miles to the Gokteik gorge. No less than three steamers were required to transport the 4,308 tons of steel, together with some 200 tons of requisite tackle for erection, and 35 American bridge-erectors.
When the Americans arrived on the scene they were treated to their first experience of Indian weather. The rain fell in torrents; the roads were converted into rushing streams, and the low-lying stretches of land into lakes. This was something new to the Americans, and they chafed at being compelled to sit down to wait until the weather moderated. To make matters worse, the line was knocked about severely by the rain, no less than thirteen wash-outs occurring between the coast and the gorge. In one place a locomotive got caught. It could not advance and could not retreat, owing to breaches in the railway on either side, so quietly settled down to rest in the waterlogged embankment, and finally slipped into a field of rice, to the intense disgust of the owner.
The result was that the port became congested with the steel and tackle awaiting dispatch up-country. The railway company repaired the wash-outs with all possible speed, and directly the line was opened the material poured towards Gokteik in a ceaseless stream. In fact, the American engineers were somewhat perplexed by the speed with which the material was sent up, and they had a spirited task in sorting out the pieces of steel as they arrived. The work proceeded so feverishly that the empty trains could not be backed out of the shunting-yard with sufficient alacrity to admit incoming loads. The bridge-builders extended assistance in a novel manner. Shunting was abandoned. The large steam derricks picked up the empty cars bodily off the one track, whipped them round, and deposited them upon a siding, from which the engines pulled them out as best they could.
Photo by permission of Pennsylvania Steel Co.]
THE GOKTEIK VIADUCT UNDER CONSTRUCTION
The railway track is 825 feet above the level of the Chungzoune River, which flows through a tunnel beneath the bridge.
The railway company provided the builders with a special railway down the side of the cliff, as the approach was not completed. This was a huge switch-back, where the trains ran from side to side, first forwards and then backwards. The descent of the precipice in this manner treated the bridge-builders to an exciting ride, which somewhat unnerved them at first, as it was far and away too thrilling to be pleasant. A cableway was also stretched across the gulch, and this was used for transporting material from point to point. In fact, two locomotives were dismantled and sent across this rope in pieces to be re-erected on the opposite side.
Photo by permission of Pennsylvania Steel Co.]
VIEW OF THE GOKTEIK VIADUCT
There are eighteen steel towers—the highest brings the rails 325 feet above the floor of the gorge—supporting 2,260 feet of bridging.
When the bridge-builders arrived they found that Mr. G. Deuchars, the engineer-in-chief to the railway, had completed the whole of the preparations. The concrete pedestals for the steel towers stretched across the floor of the ridge in two unbroken lines over the top of the natural bridge through which the Chungzoune River makes its subterranean way. All that the bridge-builders had to do was to set the steel.
The viaduct was built upon the overhanging principle, in accordance with the American practice, by means of a traveller. This was a cumbersome piece of apparatus weighing 100 tons, with a long arm which reached out over the gorge from tower to tower. To the native this appliance was a source of infinite wonder. When it was pushed out to its fullest extent, and the long arm appeared certain to lose its balance and to topple into the ravine, they looked on with awe; and when the Americans flew in the face of Providence, as they thought, by venturing to the outermost point to carry out their work, they shuddered. In fact, they never became accustomed to that traveller. Why it did not capsize exceeded their comprehension.
The American workmen were assisted in their operations by 350 natives brought from other parts of the country, and who were accustomed somewhat to bridge-building. Once work was brought into swing, it went forward with a rush, the steel towers springing up from their pedestals to a height of 200 feet or so within two or three days. The men toiled 9¾ hours every day, and there was not a halt except when the monsoon blew and it was well-nigh impossible to secure a foothold in exposed positions, or when the torrential rainfall prevailed.
The white men found the heat particularly trying and exhausting. Those perched 200 or 300 feet in the air, and fully exposed to the sun and a temperature of 120 degrees, secured a little welcome shade under an awning that was stretched over the apparatus. They wore the lightest of clothing, while white pith helmets served to offer some protection from sunstroke.
The total length of the work is 2,260 feet, and it is built up to 10 spans, each measuring 120 feet, and 7 spans of 60 feet apiece. The girders forming the deck are supported on steel towers spaced 40 feet apart. The height of the rails at the highest pier is 325 feet above the floor of the gorge, and 825 feet above the Chungzoune stream. No less than 232,868 separate pieces of steel had to be handled on the site, and the natives had to drive 200,000 rivets to secure the fabric together.
Owing to the remote point at which work was being carried out—10,000 miles by sea from home—an elaborate cable code was drawn up, each integral part of the viaduct, as well as details of the erecting plant, having a distinctive word. In addition, there were special words for the purpose of reporting the progress of the erection to headquarters. Every week the chief engineer cabled home a full progress report at a cost of 5s., or $1.25, per word. The men were provided with a well-equipped medicine chest, and a complete photographic outfit constituted an important part of the organisation, photographs being dispatched to Steelton regularly to supplement the cabled and written report on the progress of the undertaking. Only one man was lost in the enterprise, and this was attributable to fever produced from indulgence in alcoholic liquor. No other fatality was recorded either among the natives or Americans, and no serious accident marred the work, which, bearing in mind its magnitude and character, was highly satisfactory.
The actual erection occupied nine months, work being continued uninterruptedly through the wet season, when, fortunately, the greater part of the annual 150 to 200 inches of rain fell during the night. Although the viaduct is 24½ feet wide across the top, which is sufficient to carry a double track, only one road is laid at present. The bridge also enables pedestrians to cross from one side of the chasm to the other, refuge platforms being provided at frequent intervals to enable those afoot to escape being run down by passing trains. Upon completion, the structure was subjected to severe tests spread over a period of two months, and these proving satisfactory, the structure was accepted by the railway authorities. The mammoth steel traveller weighing 100 tons, and which had played such an important part in the rapid erection of the viaduct, was demolished and sold for scrap.
By the provision of this viaduct at the selected height the track is led to a natural ledge on the opposite cliff-face. While the viaduct was under construction the railhead was pushed forward, the material for the grade being transported across the valley by the overhead cable. By the time trains were able to cross the structure, the end of steel had reached a point some 35 miles beyond.
Although the viaduct is not so lofty as other structures of its class in other parts of the world, yet it occupies a position of distinct importance. Moreover, it constitutes one of the finest expressions of this class of American work that has ever been fulfilled.
CHAPTER XXI WHERE THE SNOW-PLOUGH WORKS IN SUMMER
The Scandinavian peninsula has been the battle-ground of many titanic struggles on behalf of the railway. In this country the iron horse has forced its way to the most northerly point in the world where the shriek of a locomotive whistle may be heard. This is Ofoten, a port on the Atlantic seaboard of Norway, beyond the 68th parallel, and well into the Arctic circle, where the famous iron mines of Gellivare in Sweden find a western point for shipping the ore.
It was in Sweden that steel was pressed into service for the first time in connection with the erection of bridges by the late Major C. Adelsköld, R.E., and Member of the Academy of Sciences. This was so far back as 1866, and the daring engineer designed, superintended the preparation of the metal, and also the erection of the bridge. The claim of being the first steel bridge has been advanced on behalf of other structures in different parts of the world, but the records are against all such statements, for they were anticipated by a decade at least in a convincing, practical manner.