The Railway Conquest of the World
Directly the engine-driver releases the air-brake the train commences to move. The descent is at the rate of 116 feet to the mile, and, as may be conceived, no steaming is required to give the train momentum down the banks—it travels by gravity alone, held in check by the powerful air-brake. The train plunges into a line of snowsheds, and when it emerges, two tracks at different levels may be seen, and in the far distance, on the opposite side of the valley, is the black band of steel writhing among the crags to pass from sight round a distant shoulder. The train swings down the uppermost gallery, crosses a lofty trestle set over a rift on a curve, dives into a tunnel wherein a horse-shoe loop is completed, so that when it issues from the other portal the train speeds along the second track in the opposite direction. Then it makes another twist to swing to the opposite mountain slope. Looking back from the lowest level, the line can be seen cutting three ugly gashes among the trees clothing the mountain flanks.
The construction of this series of loops was exciting, and dangerous to the navvies, as one of their number related to me. Excavation was carried out on the two levels simultaneously, but those on the lower terrace had to maintain a vigilant eye and a keen ear. Huge ballast cars were hauled on to the upper gallery loaded with debris, and they shot this over the side to build up the grade. The result was that the men below were subjected to a heavy, intermittent bombardment, for massive pieces of rock were among the spoil. These, given a start down-hill, bounced from point to point with terrific force, until they crashed into the depths of the canyon. The men had to dodge these missiles as best they could. Sometimes they were lucky; at others they were not, and many a man received a nasty wound, a jarring blow, or a broken limb from a piece of rock in flight. Accidents from this cause were numerous, and fatalities were not infrequent.
When the Western Pacific was projected it was decided to profit from the mistakes made on the early lines in the first instance. Grades in particular were to be kept down, especially among the mountains, where a maximum rise of 1 in 100 was only to be allowed. This line completes the original idea in connection with the Denver & Rio Grande line by giving the latter an outlet from Salt Lake City to the Pacific at San Francisco.
BUILDING THE BIGGEST EMBANKMENT ON RECORD BY HYDRAULIC SLUICING
The railway is 725 miles in length, and it was split into three sections for constructional purposes. The first extended from Salt Lake City to Oroville at the Pacific foot of the Sierras main range, the second from the latter point to Oakland on the coast, while the third was a trying short section right down to the water’s edge, at San Francisco from Oakland. Building was carried out on the three divisions simultaneously. Remarkable enterprise was displayed by the liberal resort to any new time- and labour-saving methods and implements. In the San Diablo Range the path of the track was interrupted by a depression 123 feet deep and 1,120 feet wide. That hollow had to be filled to preserve the grade. To expedite the task, an ingenious tool was devised. This was an electric scraper, and the idea was to pull this down the side of the mountain, thereby removing several tons of earth at a time, and to shoot it into the gulch. But the scraper did not come up to expectations. Breakdowns were so frequent that at last it was dismantled in disgust and thrown on one side to rust. Then another ingenious idea was tested. This was called a “merry-go-round,” something very similar to a roundabout. It comprised a revolving table overhanging the edge of the dump or embankment. A track was laid on the circumference of this turntable forming a loop. The laden trucks were run round this curve and their contents were shot overboard at the point desired, the empties continuing round the loop to the track to return to be refilled. The advantage of this arrangement was that the spoil could be discharged just where it was wanted much more quickly and easily than by the ordinary method, where the cars are pushed to the edge of the temporary track, emptied and then pulled back. As the bank grew outwards across the valley, the merry-go-round was pushed forwards, so that it always stood on the brink of the earthwork.
THE “MERRY-GO-ROUND” DEVISED TO EXPEDITE RAISING AN EMBANKMENT 120 FEET HIGH
A LOFTY EMBANKMENT IN COURSE OF CONSTRUCTION. IN THE CENTRE IT IS 120 FEET HIGH. CONSTRUCTION CAMP IN FOREGROUND
A NOVEL EXAMPLE OF THE RAILWAY BUILDERS’ INGENUITY
Among the mountains some magnificent work was accomplished. As the directing engineer remarked to the writer, it was a stiff problem to descend the western flanks of the Sierras with a 1 per cent. grade. The line crosses the mountains 2000 feet lower than the Central Pacific, and one advantage is that there are no snowsheds anywhere.
When one sees how rigorously the maximum grade has been guarded one marvels. The mountains are negotiated through Feather River Canyon, which is a duplicate of the Kicking Horse Pass that carries the Canadian Pacific main line down to the coast. The canyon is entered at Oroville, and for almost 100 miles the line rises steadily at 52 feet per mile, following the river until it at last gains an altitude of 4,817 feet. But hugging the river causes the line to meander very tortuously, for the waterway zigzags like the teeth of a saw.
Moreover, Feather River is a fearsome waterway. In its calmest moods it rushes along swiftly, but when swollen by the melting snows and countless mountain brooks it thunders and boils like a whirlpool. To escape the fury of the waters the track had to be laid well up the mountain-side, and where a fork of the river is crossed, a massive metal bridge had to be built for the reason advanced by the engineer that “Nothing but steel could be used with safety when the river is in full flood.”
Curiously enough, although Feather River Canyon had never before been selected as a passage-way through the mountains for the iron road, it was favoured by the Indian as being the easiest passage through the Sierras. Theodore Judah had noticed its advantages for the first trans-continental. But the Red Man’s trail was along the opposite bank to that preferred by the railway. At first sight it would appear as though the surveyors might have profited advantageously from the sagacity of the aborigines, but they declined to do so for a striking reason. The locaters had to pay due respect to the snowfall and the paths of avalanches. In such a gorge the former may be only a few inches on one, and as many feet on the other side, and the dangers from slides are proportionate. Such conditions prevail in this canyon. The bank selected by the engineers is exposed to the sun throughout the day, and the snowfall is very slight, whereas on the other and shaded bank it is very severe.
In ascending the canyon, very heavy development work had to be carried out. At one point a huge loop had to be described on the mountain-side, and the summit negotiated by a long tunnel beneath the Beckwourth Pass. The latter acts as a funnel or shaft for the warm “Chinook” winds, which, entering the pass, melt the snow almost as soon as it falls. Consequently, on this section snow is an insignificant enemy, and does not strike such terror into the hearts of the railway authorities as, say, on the Canadian Pacific, or the Overland route. The records at Beckwourth give the maximum depth of snow as 24 inches, so that Boreas will be kept within bounds very easily by an ordinary snow-plough. By placing the track well below the snow-line, and with the assistance of the kindly Japanese warm wind, the heavy expense of snowsheds has been avoided.
This is no mean saving either, for in many cases the cost of building these protective sheds has been more per mile than the railway itself sheltered within. On one line the average cost of this protection is £15,000 per mile, and it is necessary for 40 miles!
On the eastern sides of the mountains the railway runs into the ill-famed Humboldt River territory, which has proved a thorn in the sides of many railway-builders. This fine waterway at times bursts its bonds, floods the country, and finally follows a new course. In order to avoid any troubles from this cause, the line was kept well clear of the district, though it involved many artificial works such as bridges, embankments and tunnels, while the river is crossed 24 times in 185 miles.
Between the foothills of the Sierras and Salt Lake City two other mountain ranges had to be overcome—the Pequop and Torano chains respectively. A tunnel solves the first, and a striking piece of development work compasses the second. This is a horse-shoe curve 5 miles in length, which rises gently eastwards at the prescribed maximum grade. Had the engineers cut straight across as the crow flies, miles would have been saved, but the banks would have been three times as heavy. The eastern point of this horse-shoe brings the railway to the fringe of the Salt Lake desert, a rolling waste of salt and borax in which lies the inland sea of the same name, and whose waters in the distant past lapped the foothills of the Torano range. The rail strikes across the desert in a bee-line for 43 miles, the permanent way being as level as a billiard-table, with the rails resting on a solid mass of salt, 8 feet or more in thickness. This marked the first attempt to cross this dismal expanse by railway. Many a traveller essaying the perilous journey as a shorter cut to the country beyond has been overwhelmed by thirst or the intolerable heat, to lie down to his last rest, his bones afterwards being found bleaching in the glare of Old Sol, beating down from a cloudless sky.
One notable feature of this road is the tunnels. There are 42 in all, aggregating over 45,000 feet in length, while there are 40 steel bridges totalling a length of 9,261 feet. In one division among the Sierras, extending for a distance of 75 miles up the Feather River Canyon, grading ran into £20,000, or $100,000, per mile. Altogether some 40,000,000 cubic yards of earth were handled to form the grade. The contractors had to spend £20,000, or $100,000, alone to cut a wagon-road in order to transport supplies to their camps along the grade.
Contemporaneously with the construction of the Western Pacific railway, a third line—the Chicago, Milwaukee & Puget Sound—was being pressed across the continent for the purpose of bringing Chicago and the Atlantic seaboard into direct touch with the Pacific ports of Seattle and Tacoma on Puget Sound.
BUILDING THE CHICAGO, MILWAUKEE AND PUGET SOUND RAILWAY THROUGH THE BITTER ROOT MOUNTAINS