River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.
2. Syphons and Culverts.—Syphons are used to pass drainage channels or other streams under canals or other lines of communication. In the case of a masonry syphon under a stream which may be dry while the syphon is full, the weight of the arch and its solid load must be not less than the upward pressure of the water passing through the syphon. The channel sometimes has a vertical drop at the upstream side (fig. 51) and a slope at the downstream side. The slope enables any solid materials to be carried through, and facilitates cleaning out and unwatering. The drop at the upstream side does not give rise to any shock on the floor when the syphon is full, but a slope is preferable if there is room for it, and it causes less loss of head.
A culvert which is liable to run full and which has a steep approach channel (fig. 52) may become suddenly drowned on the upstream side. As soon as the water rises to the crown of the arch, the wet border of the culvert increases and this reduces the velocity and discharge. The water coming down the approach channel then rises abruptly, and the increased section of the stream causes a reduced velocity of approach, and this further reduces the discharge through the culvert. The heading up continues until the difference in the upstream and downstream water-levels is great enough to readjust matters (Min. Proc. Inst. C.E., vol. clxxxvi.). The possibility of this heading up occurring should be attended to in the design. In the case of a culvert in a railway embankment where heavy floods have to be passed, the culvert may be made bell-mouthed by a curved embankment constructed on its upstream side.
3. Training Works.—The object of the upstream and downstream protections already described (Chap. X.) is to prevent damage to the structure owing to the disturbance caused by the structure itself. When a river is given to shifting its course (Chap. IV., Art. 9) and cutting away its banks, protection of another kind is required. The stream, if left to itself, may cut away one bank upstream of the structure for a long distance, and eventually damage, or destroy by undermining, the upstream pitching and the abutment itself. This is known as outflanking. If in the neighbourhood of the line A B (fig. 53) there is nothing for the river to damage,—if, for instance, the structure is a weir with a canal, if any, only on the opposite bank of the river,—and if the land is of no particular value, the case could conceivably be met by protecting the abutment on all sides, but even then there might be a chance of the erosion of the bank continuing until the stream had formed a connection at C with the downstream reach. This, of course, in the case of a weir, would render the work useless and might even destroy it.
In the case of a bridge carrying a road or railway, or of a syphon or aqueduct carrying a canal or other stream, it is wholly inadmissible to allow the stream to cut away even as far as the point A for fear of its severing the line of communication. Thus in every case it is practically necessary to prevent any serious erosion of the bank upstream of the structure. In ordinary cases it is sufficient to protect the bank C D by any of the methods given in Chap. VI., Art. 3, the protection being turned inwards, as shown at D, to prevent the end of it being damaged.
In the case of railway bridges across the great shifting rivers of India, protection used at one time to be afforded by various systems of spurs. This has now been abandoned in favour of Bell’s guide banks (fig. 54), which are found to be far more satisfactory. These guide banks are discussed in the paper by Spring quoted above (Art. 1). The spaces behind the guide banks become filled with water, at least during floods, and are meant to be silted up. An opening in the railway embankment should be provided at A, and another on the opposite side of the river, to ensure a constant flow of water (Chap. V., Art. 3), but they should not be large enough to cause high velocity. The chief danger to which a guide bank is liable is outflanking when the stream assumes the position shown. To guard against this danger it is necessary to have very strong and massive heads to the guide banks. When the bank of the eroding stream, downstream of the guide bank head, becomes a semicircle or thereabouts, the stream takes a short-cut across the sandbank, and to encourage this an artificial cut can be dug, at the season of low water, on any suitable line.
If the guide banks were made with an increased width of opening at the upper end, this would reduce the chance of outflanking but would increase the danger from a direct attack such as indicated, in the figure, on the left bank. It has been suggested that the width at the upstream end should be less than at the bridge, but this seems undesirable. Probably the form shown in fig. 54 is the proper one. The length of the guide bank upstream of the bridge is made about equal to the span of the bridge between the two guide banks. If made less than this, the river might cut into the line of railway. The length of guide bank downstream of the bridge is generally 300 to 500 feet, being greater as the velocity of the river is greater and the sand of its bed finer.
The Bengal Dooars Railway runs near the foot of the Bhutan Himalayas, and crosses some broad river channels which, after the excessively heavy rains which occur, are filled by streams of very high velocities. One such channel or set of channels (fig. 55), more than half a mile wide, is provided with a bridge whose waterway consists of ten spans of 60 feet each. The railway embankment across the remainder of the channel having been breached in many places in 1903, protection was afforded by T-headed spurs and other groynes, the first arrangement, which withstood the floods of 1904, being as shown in the figure. The triangular apex of the A-shaped groyne, south-east of the bridge, was added in 1905 because, in its absence, the water struck the bridge obliquely. After the addition there was a great deposit of silt in the neighbourhood of the four T-headed spurs. Next year the river, in a great flood, rose over the top of the railway embankment near these spurs, and finally caused a breach 600 feet wide. The embankment was afterwards raised. The velocity through the bridge seems to have approached 18 feet per second. The bridge had at first no floor. A floor was added, but was much damaged by the floods (Min. Proc. Inst. C.E., vol. clxxiii.). The level of the floor is not given, but it would seem to have been desirable to make it at a very low level. The rising of the stream over the railway embankment was attributed to the silting up near the T-headed spurs. The addition of the triangular portion above referred to would seem to have somewhat assisted this process. If all the trouble could have been foreseen, it might have been best to build an additional bridge 2000 feet south-east of the existing bridge. The groynes were composed of the wire-network rolls, described in Chap. VI., Art. 3, piled pyramid fashion.
CHAPTER XII DRAINAGE AND FLOODS
1. Preliminary Remarks.—Arts. 2 and 3 of this Chapter deal with the calculation of flood discharges, Art. 2 dealing with small streams, in which the water has to be got rid of, and Art. 3 with large streams. The remaining articles discuss the methods of predicting floods and of preventing them from doing damage. When the discharge figures have been arrived at in any case, the necessary masonry works can be designed in accordance with the principles described in Chaps. X. and XI. For remarks regarding the design of channels and banks, see Chap. IX., Art. 4, and also Art. 6 of the present Chapter.
In England, land near a stream or flooded area is said to be “awash” when the flood water rises to within 3 feet of the surface of the ground. The drainage of such land is apt to be unsatisfactory. If land is flooded or awash, it may be desirable to shift the outfall of a branch drain to a point lower down in the main outfall.
2. Small Streams.—In dealing with small streams, such as branch drains or natural streams not far from their sources, the engineer is concerned only with their maximum discharges. He has to design culverts, bridges or syphons to pass the streams under roads or other works, or to design channels or waste weirs for them. In a settled country there may be already some works in existence on the same stream, and these may form a guide, or it may be possible to obtain local information as to the height or volume of floods. Even in such a case rainfall figures will be most useful. In districts where there is no settled population, and in any case where the stream is ill-defined, and the flow fitful, the rainfall figures may afford the only, or at least far the best, means of estimating the discharge.
The rainfall to be considered in all these cases is the maximum likely to fall in a short period of time. The catchment areas dealt with are small, say 5 square miles or less. It must be assumed that the fall of rain extends to all parts of the catchment area, and that its duration is sufficient for the water from all parts of it to reach the site of the work. The different valleys or divisions of the catchment area should be considered separately, and regard must be had, not only to the area of each division, but to its length and declivity measured along the course of the stream which drains it. On these two factors depend the time taken by the rain water to reach the site of the work. The rate at which the rain water flows over the ground into rills or small subsidiary streams may be taken to be ¼ mile per hour in flat land, and 1 mile per hour on steep hill sides. The velocity of the current in the rills and larger streams is generally 2 to 4 miles per hour. It can, when necessary, be calculated roughly from the size and slope of the stream. To be on the safe side, the highest probable figure can be taken.
The time taken by the water to flow from the furthest points of the catchment area to the site of the work having been arrived at as above, the next thing is to estimate the probable maximum intensity of the rainfall during that time over the whole catchment area. The only figures immediately available will be the mean annual rainfall, or perhaps the maximum fall in twenty-four hours, but it has been shown (Chap. II., Art. 5) how the probable maximum fall over a shorter period may be estimated.
The next thing to be calculated is the “run-off,” i.e. the probable proportion of the rainfall which will at once run off. This may be less than the proportion which will eventually become “available,” because some of it may go to feed the underground supply from which springs are fed. The proportion running off a small area in a short time would, under most circumstances, be rather difficult to estimate, but in the case under consideration, only the probable maximum figure is required. This occurs when the ground is saturated. Under these circumstances the ratio of the run-off to the total fall may be somewhat as follows:—