Fig. 12.
Fig. 13.

When fascining is used, long twigs are made into bundles and tied up at every 2 feet so as to form fascines about 4 to 6 inches thick, and these are laid on the slopes and secured by pegs driven in at short intervals, between the fascines.

Fig. 14.
Fig. 15.

Sometimes the pitching or loose stone is not carried up to the top of the bank, or even up to high flood-level, and the bank above the pitching is protected by turfing—the pieces of turf being placed on edge normally to the slope if very steep (fig. 14) or laid parallel to the slope if it is not very steep—or, above ordinary water-level, by plantations of osiers or willows which obstruct the water and tend to cause silting, and whose roots bind the banks together.

Fig. 16.

Another method of using fascines is to lay them on the slopes with their lengths normal to the direction of the stream. The upper end of a fascine is above low water, and the lower end extends down to the bed of the stream. Sometimes large ropes made of straw, or rough mats made of grass, are laid on the slopes and pegged down, or mattresses of fascines are laid on the slopes and weighted with stones.

Fig. 17.

A deep recess in the bank (fig. 16) can be filled in, before the protection is added, with earth well rammed. On the Adige the filling material consisted (fig. 17) of faggots filled with stones, small cross dams being made at intervals, as shown by the dotted lines, to arrest flood water and cause it to deposit silt. At the back of the berm, poplar or willow slips were planted, and these grew up and their roots held the bank together. This system succeeded well.

A method of protection which is suitable when the water contains much silt is what is known in India as bushing. Large leafy branches of trees are cut and hung, as shown in fig. 18, by ropes to pegs. They must be closely packed so as not to shake. At first they require looking after, but silt rapidly deposits and the branches become fixed and no longer dependent on the ropes. If the work is carefully done, the result is a smooth, regular, and tenacious berm, as per dotted line in the figure.

Fig. 18.
Fig. 19.

Another method, used on canals, is to make up the bank with earth and to revet it with twigs or reeds, as shown in fig. 19. The foundation must be taken down well below bed-level, otherwise the work may slip. This kind of work cannot be done except when the canal is dry.

If the bank consists of sand or of very sandy soil, it must in any case have a flat side slope such as 3 to 1. If the sand is in layers alternating with firm soil, it is a good plan to dig out some of the sand and to replace it with clods of hard earth.

Staking (fig. 20) may be used, the stakes being one or two feet apart from centre to centre, and long twigs laid horizontally being passed in and out of the stakes, or bushing filled in behind the stakes. But bushing alone is cheaper and nearly as good.

Fig. 20.

For protecting the banks of the Indus it has been proposed (Punjab Rivers and Works, Chap. IV.) to use trees in exactly the same manner as bushing, the trees being grown in several rows parallel to the river so that whenever the river, by eroding its bank, comes up to the lines of trees the first row will fall in. The first row would be chained to the second, which would take the place of the pegs used in bushing. The other rows would remain as a reserve.

The Villa system of bed protection (Chap. V., Art. 6) has also been successfully used for bank protection on the Scheldt, and on the Brussels-Ghent Canal, the prisms being about 10 × 10 × 4 inches, and having overlapping joints. The bands of prisms are placed in position by a boat, the bands unrolling over a drum. The boat is provided with an oscillating platform carrying rollers at its end. A thin layer of gravel is laid over the bank and is pressed down by the rollers before the prisms are laid on it (Min. Proc. Inst. C.E., vol. cxxxiv., and vol. clxxv.).

In the case of the river mentioned in Chap. XI., Art. 3, where extremely high velocities were met with, cylindrical rolls of wire-netting were made, each 50 feet long and 5 feet in diameter, and filled with boulders. These rolls can be used for bank protection. The netting was made by wires 6 inches apart, crossing each other at right angles and tied together at the crossings by short pieces of wire.

Fig. 21.

On ship canals a berm (fig. 21) is frequently made a few feet below the water-level. It serves as a foundation for the pitching, which need not usually extend down to more than 5 feet below the water-level. Below that the wash has little or no effect on the banks. On ordinary navigation canals a similar berm is sometimes made—one or two feet in width and a foot or less below the water-level—and rushes are planted on it.

Sometimes a bank has been protected by a kind of artificial weed, consisting of bushes or branches of trees attached to ropes. The end of the rope is fastened to the bank and the weeds float in the stream alongside the bank.

To protect a bank from ice, which exercises an uplifting force on pitching, use has been made of a covering of a kind of reinforced concrete consisting of slabs of concrete with wires embedded in it, and fastened to the bank by wires, 20 inches long, running into the bank, these wires being embedded in mortar so as to act like stakes.

Fig. 22.

4. Heavy Stone Pitching with Apron.—On the great shifting rivers of India a system of bank protection is adopted, consisting of a pitched slope with an apron (fig. 22). The system is used chiefly in connection with railway bridges or weirs, but it has been used in one instance, that of Dera Ghazi Khan, for the protection of the bank near a town. When, as is usual, the flood-level is higher than the river bank, an artificial bank is made. In any case the bank is properly aligned. The pitching has a slope of 2 to 1, and consists of quarried blocks of stone loosely laid, the largest blocks weighing perhaps 120 lbs. The apron is laid at the time of low water on the sandbank or bed of the stream. If necessary, the ground is specially levelled for it. It is intended to slip when scour occurs. The following dimensions of the apron are given by Spring (Government of India Technical Paper, No. 153, “River Training and Control on the Guide Bank System,” 1904). The probable maximum depth of scour can be calculated as explained in Chap. XI., Art. 3. If this depth, measured from the toe of the slope pitching is D, and if T is the thickness considered necessary for the slope pitching, then the width of the apron should be 1·5 D, and its thickness 1·25 T next the slope and 2·8 T next the river. It will then be able to cover the scoured slope to a thickness of 1·25 T. This thickness is made greater than T because the stone is not likely to slip quite regularly. The thickness T should, according to Spring, be 16 inches to 52 inches, being least with a slow current and a channel of coarse sand, and greatest with a more rapid current and fine sand; but since the sand is generally finer as the current is slower, it would appear that a thickness of about 3 feet would generally be suitable. Under the rough stone there should be smaller pieces or bricks. Along the top of the bank there is generally a line of rails so that stone from reserve stacks, which are placed at intervals along the bank, can be quickly brought to the spot in case the river anywhere damages the pitched slope.

For the special protection to banks required near weirs and similar works, see Chap. X., Arts. 2 and 3.

CHAPTER VII DIVERSIONS AND CLOSURES OF STREAMS

1. Diversions.—When a stream is permanently diverted the new course is generally shorter than the old one, and the diversion is then often called a cut-off. The first result of a cut-off is a lowering of the water-level upstream and a tendency to scour there, and to silt downstream of the cut-off. Fig. 23 shows the longitudinal section of a stream after a cut-off A B has been made. The bed tends to assume the position shown by the dotted line. If both the diversion and the old channel are to remain open, the water-level at the bifurcation will be lowered still more, and the tendency to scour in the diversion will be reduced.

Fig. 23.

If the material is soft enough to be scoured by the stream, it is often practicable to excavate a diversion to a small section and to let it enlarge itself by scour. This operation is immensely facilitated if the old channel can be closed at the bifurcation. The question whether the scoured material will deposit in the channel downstream of the diversion must be taken into consideration; also the question whether the diversion will continue to enlarge itself more than is desirable. The velocity in the diversion will be a maximum if its section is of the “best form,” i.e. if its bed and sides are tangents to a semicircle whose diameter coincides with the water surface, but this may not (Chap. IV., Art. 6) be the section which will give most scour. In order to prevent the enlargement of the diversion taking place irregularly, the excavation can be made as shown in fig. 24, water being admitted only to the central gullet. The side gullets should not be quite continuous, but unexcavated portions should be left at intervals, so that if the water in scouring out the channel breaks into the gullet, it will not be able to flow along it until it has broken in all along.

Fig. 24.

If a diversion is made, not with the object of lowering the water-level but merely in order to shorten the channel, the increased velocity caused by the steepened slope may be inconvenient. In this case a weir or weirs can be added (Chap. VIII., Art. 4).

If the water contains sufficient silt to enable the abandoned loop to be silted up within a reasonable time, it may be desirable to do this. The silting up may, for instance, increase the value of the land. The loop should be closed at its upper end. Water entering the lower end will cause a deposit there. When the lower end is well obstructed by silt, the upper end should be opened.

The set of the stream, due, for instance, to a bend at the point where a diversion takes off has very little to do with the quantity of water which goes down the diversion. The only effect of the set of the stream is a slight rise of the water-level as compared with the opposite bank. Similarly, the angle at which the diversion takes off is only of importance in giving, in some cases, a velocity of approach whose effect is generally small. The distribution of the water between the diversion and the old channel really depends on their relative discharging capacities. If the required quantity of water does not flow down a diversion it can be dredged.