Account of the Skerryvore lighthouse
From this book
During the first half of the season 30 men were engaged 14 hours a day in the preparation of Foundation-pit. the foundation-pit, which, as already said, was a work of the greatest labour. The Rock, indeed, was in many places so hard as often to make it seem hopeless that tools could make any impression on it. The time employed in the excavation and the number of tools expended on it, were very great, as a pick seldom stood more than three strokes in the harder quartzose veins; but our perseverance was at length amply rewarded by obtaining a foundation so level and so fairly wrought throughout the whole area of a circle 42 feet in diameter, as to present to the view the appearance of a gigantic basin of variegated marble; and so much pleased were the workmen themselves with the result of their protracted toil, that many of them expressed serious regret that the foundation must soon be covered up so, as (we trusted), never to be seen again. In the dressing of the Rock much inconvenience arose from the small splinters which flew out before the tools, sometimes rising to the height of 40 feet, and coming in at the windows of the Barrack; and after several injuries had been sustained, I at length found it necessary to send to Glasgow for fencing masks to protect the men’s faces. In all our work, nothing was more grudged than the occasional loss of half a day in baling out the water from the foundation-pit after it had been filled by a heavy sea.
Landing of materials on the Rock. Before we had made an actual trial of landing stones on a Rock at the distance of 12 miles from the nearest shore, exposed to the incessant beating of Atlantic waves, there was much room for doubt as to the measure of success to be expected; and, as the time approached, I naturally looked to the attempt with increasing anxiety, as to an experiment in a great measure decisive of the future complexion of our operations. Four small vessels, carrying from 16 to 19 tons, had been built at Leith and Dumbarton, for the purpose of carrying the stones on their decks, so as to admit of their being easily lifted by the crane, and so to avoid the risk which would have been incurred by any attempt to raise stones by a crane from the hold of a vessel moored to a rock in the open sea and moving about with every wave. Had that been attempted, the crane would, on many occasions, have been pulled down before the stone could be cleared from the hold. The vessels were very similar to those which were used for the same purpose at the Bell Rock; and I therefore beg leave to refer the reader to page 509, and to Plate XI. of my Father’s account of that work, for a description of them. Being decked all over, to give room for cargo (for they carried nothing in the hold but empty casks for the purpose of floating them in the event of their sustaining any injury), they were towed between Hynish and the Rock by the steamer, and being cast off as near the landing-place as possible, were taken by the boats to the creek, and moored with warps to the fenders at the quay.
The first trial of the lighters in landing stones on the Rock was made on the 20th of June, on which occasion both the steamer and the stone craft were decorated with flags; and due honour was done to the occasion of landing the first stone, by firing a salvo shot and drinking success to the works. The landing service throughout the whole progress of the works was one of much difficulty and anxiety and many narrow escapes were made; but it was managed with great prudence, and at the same time with unremitting energy, by Messrs Macurich and Heddle, in their several departments, both ashore and afloat. On many occasions the men who steered the lighters ran great risks; and it was often found necessary to lash them to the rails, to prevent their being thrown overboard by the sudden bounds of the vessels, or being carried away by the weight of water which swept their decks as they were towed through a heavy sea. Sometimes, also, we were forced, owing to the rush of the sea into the creek, which threatened to lift the vessels on the top of the Rock, to draw out the loaded lighters from the wharf without landing a single stone, after they had been towed through a stormy passage of 13 miles; and one day, during the very best part of the season, so sudden was the bounding of the vessel before the sea, that eight large warps were snapped like threads as the lighter was carried violently before a crested wave which rolled unexpectedly into the creek, while those who stood on her deck were thrown flat on their faces and imagined that the vessel had been laid high and dry on the top of the Rock. During the whole season, however, in the course of landing 800 tons of masonry on the Rock, too often in that dangerous manner, none of the dressed stones received any great damage, nor was any other injury of importance sustained.
The building of the Tower was commenced on the 4th July; Building the first stone. but it was not till the 7th that the ceremony of laying the foundation-stone was performed by His Grace the Duke of Argyll, who, as proprietor of the adjacent Island of Tyree, took a great interest in the success of the works, and on that day visited the Skerryvore with the Duchess of Argyll, the Marquis of Lorne, Lady Emma Campbell, and a party of friends, in the Toward Castle steamer. On that occasion His Grace expressed himself much pleased with the works and kindly left with me a donation of L.10 for the workmen.
The building operations in 1840 were entirely carried on by means of two cranes with moveable jibs, of which one was fixed just beyond the foundation, at the place shewn in Plate III., between the landing quay and the Tower, and was chiefly used in bringing forward the materials; and the other, placed in the centre of the Tower, served for laying the stones, and was raised along with the rise of the building. So perfectly had the stones been dressed in the workyard at Tyree, that no alteration or paring of the beds or joints was required; and such was the facility afforded by the building apparatus, that by working 14 hours, we occasionally set, through the activity of Mr Charles Stewart, the foreman builder, so many as 85 blocks in a day. The first course of masonry was laid by means of a wooden trainer; but the place of all the subsequent stones was, as already noticed, regulated by the use of plumb-templets, whose inner faces were arcs of the generating hyperbola. By those means we succeeded in setting, in a most perfect manner, six courses, which carried the building to the height of 8 feet 2 inches, and contained a mass equal to 10,780 cubic feet. That quantity is not greatly less than the whole materials of the Eddystone Lighthouse Tower, which, according to my computations from the drawings of Smeaton, do not exceed 13,300 cubic feet, and is somewhat more than one-third of the contents of the Bell Rock Tower, which are about 28,500 cubic feet. That frustum was also nearly equal to one-fifth part of the whole mass of the proposed building, which is about 56,000 cubic feet. Of the six courses, the first three are of Hynish gneiss, and the rest are of granite from the Ross of Mull. The comparative merits of those two materials may be stated as follows:—The Hynish stone is harder, and susceptible of finer workmanship, and perhaps its most perfect blocks are more durable; but it requires much more labour in dressing than the Mull granite, which is more homogeneous in its structure and is not intersected by hard veins, like those which occur in the gneiss of Tyree. There is good reason also for concluding that the Mull stone is sufficiently durable, because it contains but a small proportion of micaceous matter, and in its texture closely resembles some of the blocks of St Oran’s chapel in the neighbouring Island of Iona, which have resisted the action of the weather, it is believed, for more than 600 years and still retain the marks left by the tools of the workmen. I had also carefully compared the density of the Hynish and Mull stones, by weighing blocks of known dimensions, and found that it requires 13·16 cubic feet of the former, and 13·66 cubic feet of the latter to weigh one ton, a difference much less than the appearance of the stone would lead one to expect. A Tower of the dimensions of that at Skerryvore, built entirely of Hynish stone, would have weighed about 4308 tons, while the same mass of Mull stone would weigh 4252 tons, leaving a difference of not more than 156 tons in favour of the Hynish stone.
The mortar employed in the building was composed of equal parts of Aberdda lime and Pozzolano earth, and was therefore identical, in its composition, with that used by Smeaton at the Eddystone. Not having been able, after searching the neighbouring islands, to obtain good sand, I found it inexpedient to adopt the proportion of equal parts of lime, sand, and Pozzolano, which were so successfully used at the Bell Rock; but so perfect was the adhesion of the mortar used at the Skerryvore, that in that mass of 800 tons only two small leaks were discernible, which being ripped or opened with an iron, and allowed to run dry, were afterwards carefully repointed, and have never since shewn the slightest symptoms of leaking.
CHAPTER VII. OPERATIONS OF 1841.
Hynish workyard. The workyard at Hynish presented a very busy scene during the summer and winter of 1840; and the desolation and misery of the surrounding hamlets of Tyree seemed to enhance the satisfaction of looking on our small colony, where about 150 souls were collected in a neat quadrangle of cleanly houses, conspicuous by their chimnies and windows amongst the hovels of the poor Hebrideans, who generally make no outlet for the smoke in their gloomy dwellings, but permit it to escape by the doors. The regular meals and comfortable lodgings and the cleanly and energetic habits of the Lowland workmen, whose days were spent in toil and their evenings, most generally, in the sober recreations of reading and singing, formed a cheering contrast to the listless, dispirited, and squalid look of the poor Celts, who have none of the comforts of civilized life and are equally ignorant of the value of time and the pleasures of activity.
The number of masons employed in 1841, varied from 60 to 84 and they were chiefly engaged in dressing blocks for the Lighthouse-Tower, in discharging the cargoes of vessels loaded with stone from Mull and also in shipping stones for the Rock, in which operation, their acquaintance with the handling of dressed materials and their readiness in working the cranes, made them very useful in directing and also in working along with the native labourers, who, partly from incapacity and partly from excessive indolence, could not be trusted for a moment to themselves. During that year, upwards of 38,000 cubic feet of granite were dressed into blocks with straight beds and joints, and with faces of double curvature, so as to suit the contour of the Tower, when arranged in the wall. The blocks were also fitted with stone joggles, for retaining them in their places, and with lewis-holes for raising them in the manner usually practised in building materials of that description. Of those materials upwards of 70 blocks were floor-stones (see Plans of 84th and 85th courses, Plate VIII.), dovetailed on the heads, checked on the joints and having a plain surface on the upper and a concave one on the under bed. The necessity of preserving throughout their entire joints a perfect uniformity of bearing, made the dressing of those materials a work of great nicety; and each stone, as before noticed, being cut according to moulds, was fitted temporarily in its place on the platform at Hynish, previously to its being laid aside as ready for transport to the Rock. Those various operations were conducted with great care; and the stones, which were regularly arranged and numbered according to a schedule, formed, at the time I left the workyard in the end of October, a considerable pile, bearing ample testimony to the diligence and zeal of Mr James Scott, the foreman of the workyard and leader of the party ashore.