How many data centres has local opposition actually stopped? Why the trackers disagree
At least 70 US data centre projects since January 2024, by the only list anyone can check, and probably more. That list, kept by the consultancy Relae, counts projects blocked, withdrawn or stalled; 55 ended in a withdrawal, a denial or a ban, and 15 are stalled or came back smaller[1][2]. Heatmap Pro's private count already reached 53 cancellations from 2023 to March 2026[3][4]. Data Center Watch counts 120 projects "blocked or delayed" in the first half of 2026 alone, because it includes delays[5][6]. All agree the number is rising fast.
Last updated 25 November 2026. The trackers publish quarterly; the next figures may change these.
What we know
- Cancellations climb every year. Heatmap Pro counts 2 cancellations after local protest in 2023, 6 in 2024 and 25 in 2025[10], then at least 20 in the first quarter of 2026 alone[11]. Relae's list shows 15 stopped in the second quarter and 16 in the third[12].
- Opposition often wins. Heatmap estimated in January that about 40% of projects facing sustained local opposition are eventually cancelled[13]. In October it said about half of the projects that met backlash in 2026 were cancelled[14].
- Local governments now do the stopping. In Relae's third-quarter count, 11 of 16 projects ended in a formal denial or a zoning ban. Before that, the usual ending was the developer withdrawing[15]. Heatmap says most cancelled projects fail to get a local permit[16].
- Virginia and Indiana lead. They tied for most cancellations in Heatmap's 2025 count[17]. In Relae's list Virginia has 14 of 70 projects and Indiana 7[18].
The trackers, side by side
| Who | Latest count and window | What counts as "stopped" | List public? |
|---|---|---|---|
| Data Center Watch (10a Labs)[19] | At least 45 projects, about $68B, Apr–Jun 2026[20]; 75, about $130B, Jan–Mar[21] | Blocked or delayed. Dollar totals use publicly disclosed values[22] | No. Project-level data is sold[23] |
| Heatmap Pro | At least 20 cancelled Jan–Mar 2026[24]; at least $260B cancelled Jan–Sep 2026[25]; 25 in 2025[26] | Cancelled after sustained local opposition; all data centres, not only AI[27] | No. Paid data service[28] |
| Relae (formerly Carbon Direct) | 70 projects, about $271B, Jan 2024 to Oct 2026[29]. June report: 46 AI projects, $137–172B, to 15 May 2026[30] | Blocked, withdrawn or stalled indefinitely; not projects still under review[31] | Yes. We downloaded and counted it[32] |
| Uptime Institute | 4 cancelled in 2026 plus 4 unlikely, as of 26 Feb 2026[33] | Cancelled, with public opposition playing "a key role"[34] | No. Paywalled[35] |
Why the counts disagree
- Delayed is not cancelled. Data Center Watch counts projects "blocked or delayed"[36]. Relae and Heatmap count only projects that were stopped. That alone explains most of the gap: 75 against 20 and 10 for the same quarter[37][38][39].
- Different searches find different projects. Heatmap says its researchers call every US county[40]. Relae builds from news, meeting records and other trackers[41]. For 2025, Relae's list now shows 19 stopped projects; Heatmap counted 25[42][43].
- AI or all data centres. Carbon Direct's June report counted only AI projects of at least 100 megawatts or described as serving AI[44]. Heatmap counts all data centres[45].
- Dollars are estimates. Relae's $271 billion includes $183 billion that developers disclosed; the rest is estimated from megawatts or floor space[46][47]. 20 of its 70 projects carry no value at all[48]. Heatmap says only about 60% of projects disclose an investment figure[49]. All these figures are announced plans, not money spent.
What opponents say they object to
The trackers rank concerns differently. Heatmap, reading press accounts, found water the most cited, followed by electricity prices and noise[50]. Relae, coding hearing testimony and meeting minutes in 44 stopped projects, found secrecy and attachment to place led more often; water was present in most cases but led in only one[51]. Tax breaks also draw fire: in Virginia, senators backed repealing a data centre tax break worth about $1.6 billion a year[52].
| Concern | Heatmap: press accounts, 2025 | Relae: 44 cases studied | Relae list: mentions in 70 |
|---|---|---|---|
| Water | No. 1, in over 40% of contested projects[53] | Leading in 1; present in 32[54] | 39 |
| Power bills and grid | Second[55] | Leading or secondary in 29[56] | 35 |
| Noise | Third[57] | Health, noise and air leading in 5[58] | 34 |
| Secrecy, NDAs | Not ranked | Leading in 19, the most[59] | 19 |
| Tax breaks, deal terms | Not ranked | Economic terms leading in 4[60] | 4 |
Last column: our keyword count of the concerns Relae lists for each project[61]. A project can name several.
What is still unknown
- How many stopped projects were built somewhere else. No tracker follows this. In Relae's list, 7 of 70 entries note that the developer refiled, relaunched nearby, moved to another jurisdiction or kept the right to refile[62].
- What happened to the delays. Data Center Watch's 120 blocked or delayed projects in early 2026 are not split into the two[63][64].
- Whether stalled means dead. 11 of Relae's projects are stalled, for example by a moratorium or a court case[65].
What would settle it
A shared public list with each project, its outcome date and its status a year later. Today only Relae publishes its list; Data Center Watch, Heatmap Pro and Uptime sell theirs[66][67][68].
How this page was made
We read each tracker's own report page on 25 November 2026. We downloaded the project list behind Relae's map and counted it with a script that checks the totals against Relae's published figures. Relae's quarterly chart includes one project stopped in October, so its third quarter sums to 17, not 16. Carbon Direct's June report lists outcome and sizing counts that add to 47 for its 46 projects. Data Center Watch, Heatmap and Uptime counts are their own published figures; their lists are not public, so we could not check or de-duplicate them. We did not name individual developers.