The model was only 32 inches in length, and 8 inches in beam; and in order to fix all the internal fittings, of tanks, seats, crank handles, and pulleys, I had first to fit the shell plating, and then, by finally securing one strake of plates on, and then another, after all inside was complete, I at last finished for good the last outside plate. In executing the job, my early experience of all sorts of handiwork came serviceably to my aid. After many a whole night's work—for the evenings alone were not sufficient for the purpose—I at length completed my model; and triumphantly and confidently took it to sea in an open boat; and then cast it into the waves. The model either rode over them or passed through them; if it was sometimes rolled over, it righted itself at once, and resumed its proper attitude in the waters. After a considerable trial I found scarcely a trace of water inside. Such as had got there was merely through the joints in the sliding hatches; though the ventilators were free to work during the experiments.

I completed the prescribed drawings and specifications, and sent them, together with the model, to Somerset House. Some 280 schemes of lifeboats were submitted for competition; but mine was not successful. I suspect that the extreme novelty of the arrangement deterred the adjudicators from awarding in its favour. Indeed, the scheme was so unprecedented, and so entirely out of the ordinary course of things, that there was no special mention made of it in the report afterwards published, and even the description there given was incorrect. The prize was awarded to Mr. James Beeching, of Great Yarmouth, whose plans were afterwards generally adopted by the Lifeboat Society. I have preserved my model just as it was; and some of its features have since been introduced with advantage into shipbuilding.

11

The firm of Robert Stephenson and Co. having contracted to build for the Government three large iron caissons for the Keyham Docks, and as these were very similar in construction to that of an ordinary iron ship, draughtsmen conversant with that class of work were specially engaged to superintend it. The manager, knowing my fondness for ships, placed me as his assistant at this new work. After I had mastered it, I endeavoured to introduce improvements, having observed certain defects in laying down the lines—I mean by the use of graduated curves cut out of thin wood. In lieu of this method, I contrived thin tapered laths of lancewood, and weights of a particular form, with steel claws and knife edges attached, so as to hold the lath tightly down to the paper, yet capable of being readily adjusted, so as to produce any form of curve, along which the pen could freely and continuously travel. This method proved very efficient, and it has since come into general use.

The Messrs. Stephenson were then also making marine engines, as well as large condensing pumping engines, and a large tubular bridge to be erected over the river Don. The splendid high-level bridge over the Tyne, of which Robert Stephenson was the engineer, was also in course of construction. With the opportunity of seeing these great works in progress, and of visiting, during my holidays and long evenings, most of the manufactories and mines in the neighbourhood of Newcastle, I could not fail to pick up considerable knowledge, and an acquaintance with a vast variety of trades. There were about thirty other pupils in the works at the same time with myself; some were there either through favour or idle fancy; but comparatively few gave their full attention to the work, and I have since heard nothing of them. Indeed, unless a young fellow takes a real interest in his work, and has a genuine love for it, the greatest advantages will prove of no avail whatever.

It was a good plan adopted at the works, to require the pupils to keep the same hours as the rest of the men, and, though they paid a premium on entering, to give them the same rate of wages as the rest of the lads. Mr. William Hutchinson, a contemporary of George Stephenson, was the managing partner. He was a person of great experience, and had the most thorough knowledge of men and materials, knowing well how to handle both to the best advantage.

His son-in-law, Mr. William Weallans, was the head draughtsman, and very proficient, not only in quickness but in accuracy and finish. I found it of great advantage to have the benefit of the example and the training of these very clever men.

My five years apprenticeship was completed in May 1851, on my twentieth birthday. Having had but very little "black time," as it was called, beyond the half-yearly holiday for visiting my friends, and having only "slept in" twice during the five years, I was at once entered on the books as a journeyman, on the "big" wage of twenty shillings a week. Orders were, however, at that time very difficult to be had.

Railway trucks, and even navvies' barrows, were contracted for in order to keep the men employed. It was better not to discharge them, and to find something for them to do. At the same time it was not very encouraging for me, under such circumstances, to remain with the firm. I therefore soon arranged to leave; and first of all I went to see London. It was the Great Exhibition year of 1851. I need scarcely say what a rich feast I found there, and how thoroughly I enjoyed it all. I spent about two months in inspecting the works of art and mechanics in the Exhibition, to my own great advantage. I then returned home; and, after remaining in Scarborough for a short time, I proceeded to Glasgow with a letter of introduction to Messrs. J. and G. Thomson, marine engine builders, who started me on the same wages which I had received at Stephenson's, namely twenty shillings a week.

I found the banks of the Clyde splendid ground for gaining further mechanical knowledge. There were the ship and engine works on both sides of the river, down to Govan; and below there, at Renfrew, Dumbarton, Port Glasgow, and Greenock—no end of magnificent yards—so that I had plenty of occupation for my leisure time on Saturday afternoons. The works of Messrs. Robert Napier and Sons were then at the top of the tree. The largest Cunard steamers were built and engined there. Tod and Macgregor were the foremost in screw steamships—those for the Peninsular and Oriental Company being splendid models of symmetry and works of art. Some of the fine wooden paddle-steamers built in Bristol for the Royal Mail Company were sent round to the Clyde for their machinery. I contrived to board all these ships from time to time, so as to become well acquainted with their respective merits and peculiarities.

As an illustration of how contrivances, excellent in principle, but defective in construction, may be discarded, but again taken up under more favourable circumstances, I may mention that I saw a Hall's patent surface-condensor thrown to one side from one of these steamers, the principal difficulty being in keeping it tight. And yet, in the course of a very few years, by the simplest possible contrivance—inserting an indiarubber ring round each end of the tube (Spencer's patent)—surface condensation in marine engines came into vogue; and there is probably no ocean-going steamer afloat without it, furnished with every variety of suitable packings.

After some time, the Messrs. Thomson determined to build their own vessels, and an experienced naval draughtsman was engaged, to whom I was "told off" whenever he needed assistance. In the course of time, more and more of the ship work came in my way. Indeed, I seemed to obtain the preference. Fortunately for us both, my superior obtained an appointment of a similar kind on the Tyne, at superior pay, and I was promoted to his place. The Thomsons had now a very fine shipbuilding-yard, in full working order, with several large steamers on the stocks. I was placed in the drawing-office as head draughtsman. At the same time I had no rise of wages; but still went on enjoying my twenty shillings a week. I was, however, gaining information and experience, and knew that better pay would follow in due course of time. And without solicitation I was eventually offered an engagement for a term of years, at an increased and increasing salary, with three months' notice on either side.

I had only enjoyed the advance for a short time, when Mr. Thomas Toward, a shipbuilder on the Tyne, being in want of a manager, made application to the Messrs. Stephenson for such a person. They mentioned my name, and Mr. Toward came over to the Clyde to see me. The result was, that I became engaged, and it was arranged that I should enter on my enlarged duties on the Tyne in the autumn of 1853. It was with no small reluctance that I left the Messrs. Thomson. They were first-class practical men, and had throughout shown me every kindness and consideration. But a managership was not to be had every day; and being the next step to the position of a master, I could not neglect the opportunity for advancement which now offered itself.

Before leaving Glasgow, however, I found that it would be necessary to have a new angle and plate furnace provided for the works on the Tyne. Now, the best man in Glasgow for building these important requisites for shipbuilding work was scarcely ever sober; but by watching and coaxing him, and by a liberal supply of Glenlivat afterwards, I contrived to lay down on paper, from his directions, what he considered to be the best class of furnace; and by the aid of this I was afterwards enabled to construct what proved to be the best furnace on the Tyne.

To return to my education in shipbuilding. My early efforts in ship-draughting at Stephensons' were further developed and matured at Thomsons' on the Clyde. Models and drawings were more carefully worked out on the 1/4-in. scale than heretofore. The stern frames were laid off and put up at once correctly, which before had been first shaped by full-sized wooden moulds. I also contrived a mode of quickly and correctly laying off the frame-lines on a model, by laying it on a plane surface, and then, with a rectangular block traversing it—a pencil in a suitable holder being readily applied over the curved surface. This method is now in general use.

Even at that time, competition as regards speed in the Clyde steamers was very keen. Foremost among the competitors was the late Mr. David Hutchinson, who, though delighted with the Mountaineer, built by the Thomsons in 1853, did not hesitate to have her lengthened forward to make her sharper, so as to secure her ascendency in speed during the ensuing season. The results were satisfactory; and his steamers grew and grew, until they developed into the celebrated Iona and Cambria, which were in later years built for him by the same firm. I may mention that the Cunard screw steamer Jura was the last heavy job with which I was connected while at Thomsons'.

I then proceeded to the Tyne, to superintend the building of ships and marine boilers. The shipbuilding yard was at St. Peter's, about two and a-half miles below Newcastle. I found the work, as practised there, rough and ready; but by steady attention to all the details, and by careful inspection when passing the "piece-work" (a practice much in vogue there, but which I discouraged), I contrived to raise the standard of excellence, without a corresponding increase of price. My object was to raise the quality of the work turned out; and, as we had orders from the Russian Government, from China, and the Continent, as well as from shipowners at home, I observed that quality was a very important element in all commercial success. My master, Mr. Thomas Toward, was in declining health; and, being desirous of spending his winters abroad, I was consequently left in full charge of the works. But as there did not appear to be a satisfactory prospect, under the circumstances, for any material development of the business, a trifling circumstance arose, which again changed the course of my career.